Lagos-Ibadan rail: FG talks tough, orders contractors to complete project in two weeks

- The federal government gave marching orders to the contractor to deliver the Lagos-Ibadan rail line

- It also noted that it was important to get the Iju-Agbado section of the project ready this month as commercial activities become more intense

- FG, through the minister of transportation, Rotimi Amaechi, also directed that the project get ready for test-run in the next two weeks

The federal government on Thursday, January 3, gave marching orders to the contractor handling the Lagos-Ibadan rail line to deliver the Iju (Lagos) to Agbado (Ogun) section of the project within the next two weeks.

It stated that although there had been a considerable improvement on the project, it was important to get the Iju-Agbado section ready this month as commercial activities were more pronounced on the specified location, NAN reports.

Legit.ng gathers this came as the renowned economist and chief executive of financial derivatives company, Bismarck Rewane, stated that the Lagos-Ibadan rail project would reduce inflationary pressures when completed.

READ ALSO: NAIJ.com upgrades to Legit.ng: a letter from our Editor-in-Chief Bayo Olupohunda

The minister of transportation, Rotimi Amaechi, directed officials of the China Civil Engineering Construction Company to speed up work on the Iju-Agbado section of the project and get it ready for test-run in two weeks.

Amaechi said: “Getting to Abeokuta, you will see that there’s an improvement but the problem they have now is the civil work between Agbado and Iju which is critical to me because I don’t think passengers will go to Agbado to join the train.

“I believe that the closer we are to Lagos, the better for the rail and that is why I had to tell them to tell me what they will do about this before the next two weeks, although there’s a huge improvement up to this point. I want them to speed up the construction from Iju to Agbado.”

On why the contractor had yet to bring in more equipment to hasten the pace of work, the minister stated that the excuse given by the firm was that the equipment was not off-the-shelf machines that could be moved easily to Nigeria from abroad.

He also stated that the project would reduce congestion at the Lagos sea port.

Amaechi said: “Part of the solution to the congestion around Lagos sea port is an efficient rail line. You can argue that the narrow gauge is there but it is not efficient. But the moment you fix this then those goods will be transferred to the rail and then the logjam will disappear.

“The moment we do the section from Iju to the seaport, then most of those goods, especially the ones going to Ibadan will be on the rail lines.”

When asked whether the government was being pressured by Nigerians to complete the rail project, Amaechi replied: "Of course, and it is also because of the speed, for it takes you about 30 minutes by rail from Lagos to Ibadan as against over one hour by road. And this is subsidised.”

Explaining some of the impacts of the project on the economy, he said said: “This is a massive project that will have a multiplier effect when completed and will reduce logistics and distribution cost, which are the major areas of inflationary pressures in Nigeria. So I think we should give them time to complete it because it will increase productivity and reduce cost.

“It will reduce inflationary pressures because the cost of moving goods from point A to B will be reduced since you are not coming by road. So that is a good way to reduce the pressure and inflation is one of the core economic concerns for Nigeria. Therefore, anything that can reduce inflation is good for the country.”

PAY ATTENTION: Download our mobile app to enjoy the latest news update

Meanwhile, Legit.ng previously reported that the federal controller of works in Lagos state, Adedamola Kuti, said the construction cost for the section one of the Lagos-Ibadan expressway, from Lagos to Sagamu interchange had risen to N134 billion.

Kuti said this on Tuesday, December 18, at Asese and Mowe section of the project, adding that the costs of the project rose due to the additional works required in the road, which was not part of the original budget.

PAY ATTENTION: NAIJ.com (naija.ng) upgrades to Legit.ng to serve its readers better

Rotimi Amaechi gives a summary of the Buhari Administration | Legit TV

Source: Legit.ng



from Nigeria News today & Breaking Naija news ▷ Read on LEGIT.NG 24/7 http://bit.ly/2CQum2D
via EDUPEDIA24/7

Comments

Popular posts from this blog

Nigerian Academy Of Science Inducts First Female President

The Nigerian Academy of Science has inducted a professor of Parasitology/Epidemiology, Ekanem Ikpi Braide, as its 19th President on Thursday. In a statement issued by Oladoyin Odubanjo, the Executive Secretary of the Academy, Braide is the Academy’s first female President in 44 years of existence. It read, “Braide was a member of the national committee that achieved the laudable feat of guinea worm eradication in Nigeria. “She has a rich professional experience as a researcher and an administrator. In July 2010, Professor Braide was honoured by the President of Nigeria with the award of Officer of the Order of the Federal Republic (OFR) for her contribution to disease control in Nigeria. “She was nominated by the Honourable Minister of Health to serve in the Ministerial Expert Advisory Committee on COVID-19 Health Sector Response (MEACoC-HSR). “Professor Braide served as Vice-Chancellor, Cross River University of Technology (CRUTECH) Calabar, Nigeria (2004 to 2009) and as P...

NLNG Signs Letter Of Intent On Delayed Gas Expansion Project

The Nigerian Natural Liquefied Gas LTD has signed a letter of intent for the engineering, procurement and construction of its long held up Train Seven project. In a statement released by the company on Wednesday, it said that the $10bn project will be executed by a consortium of Italian firm Saipem, Japan’s Chiyoda and South Korea’s Daewoo. The statement reads, “The project will form part of the investment of over $10bn including the upstream scope of the LNG value chain, thereby boosting the much needed Foreign Direct Investment profile of Nigeria.” Managing Director of NLNG, Tony Atta, said in 2018 that the Final Investment Decision would be made in the fourth quarter of that year. This did not however, materialize. According to the release, the project will have a four to five-year execution time after the signing of the FID. The project is expected to add an extra 8 million tons per annum of gas to the 22 mtpa currently exported by the company. Oil News AddThis :...

Former Maritime Agency Boss, Buba Galadima, Accuses AMCON Of Witch-hunt After Property Takeover

  A former Director-General of the Nigeria Maritime Agency, Buba Galadima, has accused the Asset Management Corporation of Nigeria of witch-hunt after the agency took possession of his business and assets on Tuesday in Abuja. Galadima, an ardent critic of President Muhammadu Buhari, claimed that he did not borrow money or have unpaid debt with Unity Bank, which lodged a complaint against him and occasioned AMCON’s move on Tuesday. The properties taken over include House No. 15, Addis Ababa Crescent, Wuse Zone 4, Federal Capital Territory, Abuja and House No. 4, Bangui Street, Wuse 2, also in Abuja.  Reacting to the situation, Galadima said, “This is an attempt to disgrace and break me down. This is injustice and an attempt to humiliate me. "But I am unbreakable and they can never silence me. They sacked me and over 50 people that sleep in the apartment. "We don’t know where to go. We will remain on the streets. We will remain on the streets until God provi...